"Duke Energy spending on Lee nuclear plant remains slow"

As reported by John Downey in Charlotte Business Journal, Duke Nuclear's spending on "pre-construction" activities at its proposed new Lee nuclear power plant in Gaffney, SC, has been relatively low in the past couple years -- if $3-4 million per month can be regarded as "low." After all, significant energy efficiency, and even renewable energy projects, such as wind power and solar photo-voltaics, could be built for that kind of money!

Duke Nuclear had originally proposed firing up Lee Unit 1 in 2017. But now initial start up has been postponed till 2024 at the earliest.

Duke proposes to build two Toshiba-Westinghouse AP1000 reactors, just as is happening at Vogtle 3 & 4 in GA, and at Summer 2 & 3 in SC. Both the Vogtle and the Summer new reactor construction projects are billions of dollars over-budget, and years behind schedule.

Duke has not yet charged its $450 million in "pre-construction" activities to its SC rate-base, but it could under SC's generous "Construction Work in Progress" (CWIP) law.

Already, South Carolina Electric & Gas and SCANA have charged their SC ratepayers more than half a dozen rate increases, entirely devoted to CWIP costs on building Summer 2 & 3, with the SC public service commission's blessing. SCE&G and SCANA have not applied for federal nuclear loan guarantees, however.

Vogtle 3 & 4 has slogged ahead, thanks not only to CWIP surcharges on GA ratepayer electricity bills, but also compliments of an $8.3 billion federal taxpayer-backed loan guarantee, and loan. President Obama and Energy Secretary Moniz have provided that massive loan guarantee, and loan, without charging Southern Nuclear and its partners a single penny of credit subsidy fee, to protect federal taxpayers at least to some small extent, should Southern default on its loan repayment.

$8.3 billion is 15 times more federal taxpayer funding than was lost to the U.S. Treasury at Solyndra, when that solar loan guarantee repayment defaulted. But Vogtle 3 & 4 are at a significantly higher risk of defaulting, than was Solyndra when the solar loan guarantee was awarded.

More than $10 billion in nuclear loan guarantee funding remains available, for projects like Lee 1 & 2, or Fermi 3 in MI, to apply for. Lee 1 & 2 still needs COLA (combined Construction and Operating License Application) approval by NRC, something that Fermi 3 already won on May 1, 2015. However, Beyond Nuclear and allies continue to challenge the Fermi 3 license, now by appealing to the federal courts. One of the appeals by the environmental coalition is a challenge to NRC's Orwellian permission to grant the go ahead for "pre-construction" activities at new reactor construction sites, in violation of the National Environmental Policy Act.