Davis-Besse's "San Onofre-like" shortcuts on safety with steam generator replacement focus of NRC public meeting

Beyond Nuclear set up an info. table at the U.S. Nuclear Regulatory Commission's (NRC) "annual performance review" public meeting in Carroll Township, Ohio, just a few miles down the road from FirstEnergy Nuclear Operating Company's (FENOC) problem-plagued Davis-Besse atomic reactor. Beyond Nuclear was there to let the public know about the ongoing resistance by an environmental coalition to Davis-Besse's 20-year license extension, and its recently filed intervention against FENOC's San Onofre-like shortcuts on safety regarding its proposed 2014 steam generator replacements.

Toledo attorney Terry Lodge  represents the coalition, and Fairewinds Associates, Inc's Chief Engineer, Arnie Gundersen, serves as its expert witness. Gundersen also serves as Friends of the Earth's (FOE) expert, which just successfully forced Edison International to permanently shutdown the San Onofre 2 & 3 atomic reactors due to fatally flawed replacement steam generators.

WTOL's Jennifer Steck quoted Beyond Nuclear's Kevin Kamps (print articletelevision report):

'..."We want to prevent a Chernobyl or Fukishima on the shoreline of the Great Lakes," said Kevin Kamps, of Beyond Nuclear. "There is no reactor in this country that's come closer to that as many times as Davis-Besse has."

Davis-Besse is licensed for operation through 2017, and in the process of a 20-year license renewal. Delaying that renewal and preventing a steam generator replacement in 2014 are the main goals of Beyond Nuclear.

"We've long strived to shut down Davis-Besse, and we're not going to give up now," Kamps said. "We're just going to re-double our efforts."...'

The Toledo Blade's Roberta Gedert also quoted Kevin:

“They went way out of their way to avoid a license amendment on this major organ transplant,” said Kevin Kamps, radioactive waste watchdog for Beyond Nuclear. “If they have made any mistakes, they have wasted hundreds of millions of dollars because we are going to challenge them at every turn.”

Reader Comments

There are no comments for this journal entry. To create a new comment, use the form below.
Editor Permission Required
You must have editing permission for this entry in order to post comments.