« Cumulative radiation exposure risks cited as another reason to block construction and operation of "Fermi 3" | Main | Fish Eaters Threatened by Fukushima Radiation »
Thursday
Jan262012

Entergy's FitzPatrick busted for violations of radiation protection regulations

Entergy's FitzPatrick GE BWR Mark 1 on the Lake Ontario shore of upstate NYThe U.S. Nuclear Regulatory Commission (NRC) has lambasted Entergy Nuclear for violations of radiation protection regulations at its FitzPatrick atomic reactor in upstate New York on the Lake Ontario shoreline.

In a media release entitled "NRC CONFIRMS ACTIONS TO BE TAKEN AT FITZPATRICK NUCLEAR PLANT TO ADDRESS VIOLATIONS INVOLVING RADIATION PROTECTION PROGRAM," NRC addressed "actions... intended to address multiple violations involving radiation protection technicians at the Scriba, N.Y., plant...[involving] failures by the technicians to perform or properly execute their duties." These included:

"Failure by technicians to perform required respirator fit testing on multiple occasions from 2006 to 2009; a failure to maintain accurate documentation of completed respirator fit tests during the same period; a failure to perform and/or accurately document independent verification of certain valve positions after the valves were manipulated between September 2007 and December 2009; a failure to document a personal contamination event on at least one occasion; a failure to perform a contamination survey, or check, prior to the removal of an item from the plant’s radiologically controlled area; and a failure to carry out daily radiological surveys, on multiple occasions from 2006 to 2009, of a reactor building airlock."

FitzPatrick is a 38 year old General Electric Boiling Water Reactor of the Mark 1 design, identical to Fukushima Daiichi Units 1 to 4. NRC has granted FitzPatrick a 20 year license extension, as well as a power uprate.