Search
JOIN OUR NETWORK

     

     

 

 

« DOE signs $6.5 billion federal nuclear loan guarantee for Vogtle 3 & 4 | Main | Nuclear revolving door gobbles up billions of dollars of ratepayers' money, threatening to move onto taxpayers next! »
Wednesday
Jan012014

Vogtle nuclear loan guarantees drag into fifth round of delays

Aerial image of Plant Vogtle Nuclear Generating Station - photo credit to High Flyer. The photo shows the operating Units 1 and 2, as well as the construction site for proposed new Units 3 and 4.As reported by Platts, and conveyed in a Friends of the Earth press release, the December 31, 2013 U.S. Department of Energy deadline for finalization of the $8.3 billion federal taxpayer backed nuclear loan guarantee for Vogtle 3 & 4 has been extended yet again, for a fifth time, until the end of January, 2014.

As reported by FOE: "Freedom of Information Act requests and litigation revealed that the credit subsidy fee offered to Southern Company ranged from 0.8 to 1.5 percent. The credit subsidy fee is supposed to insulate against default, but the fee offered to Southern Company is woefully inadequate to cover the risks involved in major nuclear construction. According to the Nuclear Regulatory Commission, 32 percent of reactor construction is cancelled before any electricity is produced."

Watchdog groups have long called for a credit subsidy fee commensurate with the risk of the nuclear new build proposals. Congressional auditors reported several years ago that new reactors, historically, have had a 50% risk of cancellation and potential default. The Vogtle 3 & 4 nuclear loan guarantee puts 15 times more taxpayer money at risk than did the Solyndra loan guarantee scandal, which had a significantly lower risk of default than does Vogtle 3 & 4.

Vogtle 1 & 2 were the poster children for cost overruns in decades past, coming in with a price tag 1,300 percent higher than originally estimated! Vogtle 3 & 4's price tag has also skyrocketed over the past several years.

The only way that Vogtle 3 & 4 have proceeded this far is that Georgia lawmakers made legal what is illegal in most states: the gouging of ratepayers on their electricity bills with "Construction Work in Progress" (CWIP) surcharges for the building of the new reactors. This makes ratepayers unwilling investors, who receive no share of the profits that are made -- at who are put at risk of losing every penny invested, if the project ever goes belly up. Ratepayers in Florida just experienced this at the Levy new build site -- $1.5 billion lost, and nothing to show for it.

Given the Obama administration offered the $8.3 billion nuclear loan guarantee nearly four years ago, and now this latest delay, concerns continue to mount that the project is a financial house of cards, and will ultimately leave taxpayers holding the bag. Nuclear Watch South has called for taxpayers to express their concerns to decision makers, as has Beyond Nuclear.