Search
JOIN OUR NETWORK

     

     

 

 

« SACE Statement on Duke Energy Florida’s Cancellation of Levy County Nuclear Reactor Project | Main | Cooper: Duke abandonment of Levy reactors fits into 2013 pattern of "rapid-fire downsizing" of nuclear power in U.S. »
Thursday
Aug012013

Environmental interveners respond to Duke's cancellation of proposed new reactors at Levy County, FL

Washington, D.C.-based attorney, Diane Curran, represented environmental interveners NIRS and Ecology Party of Florida against the now-cancelled proposed new reactors at Levy Co., FLThe Ecology Party of Florida and NIRS, environmental interveners against Duke/Progress Energy's proposed new reactors at Levy County, FL, have responded to the announced cancellation:

The Ecology Party of Florida could not be happier that the proposed nuclear plant scheduled for construction in Levy County, Florida (LNP), has been cancelled by Duke Energy, which acquired Progress Energy Florida (PEF), the LNP applicant.  The Ecology Party, along with Nuclear Information and Resource Service (NIRS) waged a five-year battle within the confines of the Nuclear Regulatory Commission’s  (NRC) rigged system, challenging the construction of the plant. The challenge was based primarily on the fact that the water modeling used was unsuited for the karst geology at the site and that in combination with other mining projects in the area, including the nearby proposed King Road Tarmac mine which would have supplied materials for the plant. Due to this failing, the proposed LNP  would have irreparably harmed the aquifer, source of drinking water for the area. Dewatering the area further than it already has been would have resulted in impacts far more serious and far-reaching than those alleged by Progress and the NRC Staff.  The two groups presented evidence that any predictions in the Environmental Impact Statement (EIS) were inadequate and that the destructive consequences of withdrawing millions of gallons of water from the aquifer each day, as well as drawing all fresh water from the abandoned Cross Florida Barge Canal and its estuary in the Gulf had been grossly underestimated.

The Army Corps of Engineers (Corps) had not yet issued the necessary permit for the destruction of wetlands at the site and the Ecology Party, its members, and Hydroecologist Dr. Sydney Bacchus, primary expert for the Ecology Party, have been extremely active in opposing the project in the Corps' process. We believe our opposition and the compelling evidence we've submitted has had a bearing on the decision.

In response to news of the abandoned LNP project, Dr. Bacchus's reaction was, "This is an excellent example of what can be accomplished when the public refuses to accept false and inaccurate information fed to agencies by consultants and instead fights to have the truth exposed. I hope this will serve as a role model for future grass-root battles."

Diane Curran [photo, above left], who represented the Ecology Party and NIRS said, “It is great news for the environment that PEF apparently thinks Levy would be an economic disaster.  It would have been an even bigger disaster for the fragile wetlands where PEF wanted to build the reactors.”

Cara Campbell, Chair of the Ecology Party, pointed out, “The cost of this debacle had risen from 4 Billion dollars to 25 Billion. How much were the ratepayers of Florida expected to take?”

"The people, animals, plants and waters of the Nature Coast are figuratively sighing with relief that an area of recreation and sanctuary, the Nature Coast, will be nuclear-free!" said Mary Olson of Nuclear Information and Resource Service who supported efforts by Florida activists to intervene in the proposed Levy County 1 & 2 nuclear license.

Michael Mariotte, Executive Director of Nuclear Information and Resource Service (NIRS), added:

"The nuclear renaissance is in shambles. Earlier this week, the world's largest nuclear company, Electricite De France, announced it is leaving the U.S. nuclear market having failed to build any of the reactors it was planning. Now Duke Energy is giving up on the most expensive nuclear project ever proposed--and the only "greenfields" site in the supposed nuclear revival. The basic truths about nuclear power outweigh the fantasies of nuclear boosters: it remains too dirty, dangerous and expensive to be a viable source of new electricity."