NRC's Nuke Waste Confidence EIS will delay reactor licenses for at least two years!
The five Commissioners who direct the U.S. Nuclear Regulatory Commission (NRC) have just ordered NRC Staff to carry out an expedited, two-year long Environmental Impact Statement (EIS) process to revise the agency's Nuclear Waste Confidence Decision (NWCD) and Rule. Critics have charged the NWCD is a confidence game, which for decades has prevented environmental opponents of new reactor construction/operation licenses, as well as old reactor license extensions, from raising high-level radioactive waste generation/storage concerns during NRC licensing proceedings, or even in the federal courts. This EIS process and NWCD revision will thus delay any final NRC approval for new reactor construction/operation licenses, or old reactor license extensions, for at least two years.
The "Mountain of Radioactive Waste 70 Years High" conference in Chicago Dec. 1-3 will serve as a launch pad for generating public comments to NRC on this EIS, as well as to push back against the nuclear establishment's backlash proposals to begin "Mobile Chernobyl" irradiated nuclear fuel shipments by road, rail, and waterway to "consolidated interim storage." See Beyond Nuclear's pamphlet on high-level radioactive waste (cover reproduced at left). More.
Reader Comments