Search
JOIN OUR NETWORK

     

     

 

 

« French nuclear safety agency urges wider Japan evacuation | Main | Areva stops construction of reactor components plant in US »
Thursday
May192011

Finnish nuclear regulator tells Indian official of EPR problems

From The Hindu newspaper: "Union Environment Minister Jairam Ramesh heard a sobering assessment of the Areva's Finnish reactor project (pictured left) — which is running four years behind schedule, with cost overruns hitting 2.7 billion euros — from that country's nuclear regulator.

In a presentation made to Mr. Ramesh and a visiting Indian delegation in Finland earlier this week, Finnish regulator STUK put the blame for the crippling delay on Areva, for taking on the job without the requisite competencies, without experienced partners, and without completing design and engineering work before it started construction.

“In all of the Areva's earlier projects, the owner and licensee of the French nuclear power plants EdF had played the important role as the architect-engineer and had been responsible for the construction management,” The STUK told Mr. Ramesh. “at the start of the project it was found that many of the experienced nuclear manufacturers who had contributed to the earlier Areva projects had left the business. The Areva had to find new subcontractors and to coach them in nuclear manufacturing.”

The Finnish regulator added that the original schedule was “too ambitious” for a nuclear plant that is the first of its kind, larger than any previous project and built after a long gap in nuclear plant construction in Europe."