Search
JOIN OUR NETWORK

     

     

 

 

« Environmental coalition defends contentions against Fermi 3 proposed new reactor, challenges adequacy of NRC FEIS | Main | Entergy Watch: Bill in Vermont State House seeks more stringent decommissioning at Vermont Yankee »
Thursday
Feb212013

Fermi 3 Final Environmental Impact Statement incomplete: intervenors reveal major inadequacies; NRC announces major delays in Safety Evaluation Report; major setbacks projected

An artist's rendition of the ESBWR targeted to be built at Fermi 3On Feb. 19, 2013, the environmental coalition intervening in opposition to the construction and operation of Detroit Edison's proposed new Fermi 3 atomic reactor filed new and amended contentions in response to the U.S. Nuclear Regulatory Commission's Final Environmental Impact Statement about the proposal. The coalition issued a news release. As environmental coalition attorney Terry Lodge says in the press release, Fermi 3's price tag has skyrocketed to $20 billion.

An important aspect of the environmental intervention is defense of endangered species. An Eastern Fox Snake threatened species contention is set for hearing on the merits before the Atomic Safety and Licensing Board this autumn. The construction of Fermi 3, and its new transmission line corridor, could extirpate the species due to stressing or even killing Eastern Fox Snakes, as well as destroying their habitat. Additional endangered species are present at both the reactor construction site, and along the undeveloped land in the proposed transmission line corridor.

Documents related to environmental intervenors' filing of Feb. 19, 2013 in opposition to the General Electric-Hitachi so-called "Economic Simplified Boiling Water Reactor" (or ESBWR, see image, left) proposed to be constructed and operated at the Fermi nuclear power plant in Monroe County, Michigan, on the Lake Erie shoreline, as well as documents reveal the major schedule delays afflicting the project:

Intervenors' Feb. 19, 2013 "MOTION FOR RESUBMISSION OF CONTENTIONS 3 AND 13, FOR RESUBMISSION OF CONTENTION 23 OR ITS ADMISSION AS A NEW CONTENTION, AND FOR ADMISSION OF NEW CONTENTIONS 26 AND 27";

Current Fermi 3 COLA Review Schedule (Feb. 15, 2013), showing 2 years and 10 month of delay;

Original Fermi 3 Schedule (June 30, 2009).