The U.S. nuclear reactor fleet is aging but owners are applying to the Nuclear Regulatory Commission for license extensions to operate reactors an additional 20 years beyond their licensed lifetimes. Beyond Nuclear is challenging and opposing relicensing efforts.

.................................................................................................................................................................................................................

Saturday
Aug252012

FENOC weather seals severely cracked Davis-Besse shield building exterior -- 40 years too late

As reported by the Toledo Blade in an article entitled "Work crews apply waterproof coating to Davis-Besse: Project not silencing critics of plant," the only "corrective action" FirstEnergy Nuclear Operating Company (FENOC) plans to take, in response to severe cracking of its radiological containment "shield building," is to weather seal the exterior of the steel-reinforced concrete structure -- four decades too late. FENOC blames the cracking on the "brutal Blizzard of 1978,"which Beyond Nuclear has dubbed a snow job -- a charge repeated on the floor of the U.S. House of Representatives by long-time Davis-Besse watchdog, Congressman Dennis Kucinich (D-OH), whose constituents live immediately downwind and downstream from the problem-plagued plant. 

The article quoted both Terry Lodge, Toledo-based attorney representing the environmental coalition (Beyond Nuclear, Citizens Environment Alliance of Southwestern Ontario, Don't Waste Michigan, and the Green Party of Ohio) battling against Davis-Besse's 20-year license extension, as well as Beyond Nuclear's Kevin Kamps:

"I'm not at all comforted that they discovered an error that never should have happened to the most expensive and safety-significant building on the site," Mr. Lodge said Thursday.

Added Kevin Kamps of Beyond Nuclear, "It's 40 years too late. Weather sealant will not fix the cracks that are there."

As reported by Fox 8 Cleveland, a FENOC spokesman outright lied: “The shield building meets all its design parameters, we have evaluated it for all its parameters, and it is fully operable,” said Jon Hook, the design engineer manager at the plant.

In fact, both the U.S. Nuclear Regulatory Commission and FENOC itself have acknowledged that Davis-Besse's severe shield building cracking violates the atomic reactor's design and licensing bases. At an August 9th public meeting in Oak Harbor, OH, an NRC spokesman, with an audible scoff, admitted that NRC has generously granted FENOC until December 2012 to merely come up with a "plan for a plan" to "restore conformance" -- that is, pencil whip the violations, making everything appear okay on paper.  

Hook also told the Toledo Blade the shield building "wasn't coated originally because 'there was no requirement that it be done...'." Why such a basic no brainer as weather sealant was not required -- on the shoreline of Lake Erie, which suffers severe winter weather -- has never been explained, neither by FENOC nor NRC. Further deepening the mystery is the fact that all other -- much less safety significant and expensive -- concrete structures on site were weather sealed. When asked to explain, FENOC spokeswoman Jennifer Young has simply said it was done for aesthetic reasons, as those other structures appeared "splotchy." 

WNWO also reported on this story.

Friday
Aug172012

Crack contention against Davis-Besse 20-year extension bolstered by NRC FOIA revelations

At the reactor's front gate, "Homer Simpson and Humpty Dumpty act out" FENOC's "Blizzard of '78" snow job theory for why/when/how Davis-Besse's concrete containment shield building cracked. This March 24, 2012 street theater was held in solidarity with the SAGE Alliance's day of action to shut down Vermont Yankee, and protested FENOC's Feb. 28th "root cause report."The environmental coalition challenging FirstEnergy Nuclear Operating Company's (FENOC) proposed 20-year license extension at the problem-plagued Davis-Besse atomic reactor, near Toledo on the Lake Erie shore, has bolstered its contention on the severe shield building cracking by citingU.S. Nuclear Regulatory Commission (NRC) documents revealed through a Freedom of Information Act (FOIA) request submitted by Beyond Nuclear. The coalition has issued a media release about its latest contention supplementation.

Toledo attorney Terry Lodge filed this FOIA supplement, the coalition's fifth this year, since filing the original contention on January 10th, just five days after the environmental intervenors confronted NRC and FENOC about the cracking at a special public meeting at Camp Perry, OH. The others include: (1) a Feb. 27th filing, based on U.S. Rep. Kucinich's (D-OH) revelation that the shield building's outer rebar layer was no longer structurally functional, due to the cracking; (2) a June 4th filing, in response to FENOC's woefully inadequate Aging Management Plan (AMP) for the shield building's cracks; (3) a July 16th filing, in response to FENOC's revised root cause analysis report, which revealed that shield building cracking was first observed not in October 2011, but rather August 1976; (4) a July 23rd filing, based on revelations in FENOC contractor Performance Improvement International's revised root cause assessment report, which revealed 27 areas of skeptical NRC questioning about FENOC's "Blizzard of 1978" theory of shield building cracking (the environmental Intervenors also posted documents supportive of its fourth supplement). The environmental coalition also defended its crack contention, on February 14th, against challenges by NRC staff and FENOC.

Beyond Nuclear has prepared a report, entitled "What Humpty Dumpty Doesn't Want You to Know: Davis-Besse's Cracked Containment Snow Job," which summarizes the coalition's work in 2012 on Davis-Besse's dangerously degraded condition.

Wednesday
Aug152012

Kucinich demands OIG investigation of NRC's two-faced "snow job" on Davis-Besse's cracked containment

U.S. Rep. Dennis Kucinich (D-OH), a long time watchdog on the problem-plagued Davis-Besse atomic reactorU.S. Representative Dennis Kucinich (D-OH, photo at left) has written to the U.S. Nuclear Regulatory Commission's (NRC) Office of Inspector General (OIG), demanding an investigation of NRC wrongdoing in regards to its Region 3 safety engineers telling him and his staff one thing months ago about Davis-Besse's shield building cracking, and another thing last Thursday night. Rep. Kucinich's office has issued a press release about his demand as well.

Kucinich referenced Beyond Nuclear's Freedom of Information Act (FOIA) request to NRC, which has revealed, among many other things, that NRC staff worked evenings, weekends, and even through the Thanksgiving holiday, in order to rush approval for FirstEnergy Nuclear Operating Company (FENOC) to restart Davis-Besse on December 2, 2011 -- despite not knowing the "root cause," extent, and safety and environmental risk significance of the cracking in the concrete shield building, nor what corrective actions needed to be made.

Kucinich joined with environmental coalition allies seeking to block Davis-Besse's proposed 20 year license extension at a press conference in the reactor's hometown of Oak Harbor, OH, 21 miles from Toledo on the Lake Erie shore, prior to a special NRC public meeting about the cracking scandal. Beyond Nuclear unveiled a new report, "What Humpty Dumpty Doesn't Want You to Know: Davis-Besse's Cracked Containment Snow Job," which summarizes NRC's FOIA revelations. The environmental coalition's Toledo-based attorney, Terry Lodge, will file a motion this week to introduce into the record of the NRC Atomic Safety (sic) and Licensing Board operations extension proceeding these FOIA revelations.

Wednesday
Aug152012

"Crisis du jour" at Entergy Nuclear's Palisades atomic reactor

Anti-nuclear watchdogs have long called for Palisades' shutdown. Here, Don't Waste Michigan board members Michael Keegan of Monroe, Alice Hirt of Holland, and Kevin Kamps of Kalamazoo speak out at the 2000 Nuclear-Free Great Lakes Action Camp, with Palisades' cooling tower steam, as well as Lake Michigan, visible in the background

From 2005 to 2007, an environmental coalition representing hundreds of thousands of Michiganders and others throughout the Great Lakes Basin resisted the Palisades atomic reactor's 20 year license extension, only to be steamrolled by the U.S. Nuclear "Rubberstamp" Commission. Yet again, they can say "we told you so":

On Sunday, Palisades shut down due to a leak of radioactive and acidic primary coolant, escaping from safety-critical control rod drive mechanisms attached to its degraded lid, atop its "worst embrittled reactor pressure vessel in the U.S." Two years ago, in a report entitled "Headaches at Palisades: Broken Seals & Failed Heals," David Lochbaum, Director of the Nuclear Safety Project at Union of Concerned Scientists, warned about closely related problems extending back 40 years at Palisades. The CRDM leaks are so chronic at Palisades, as reflected in 20072009, and 2010 NRC PNOs (Preliminary Notifications of Occurrence), that NRC cut and paste verbage from one incident to the next, and even admitted: "While limited CRD seal leakage is not unusual for the CRD seal design at Palisades, elevated CRD seal leakage rates and increasing leak-rate trends are indicators of CRD seal degradation. The site has experienced elevated CRD seal leakage rates and increasing leak-rate trends in the past which required similar plant shutdowns."

Arnie Gundersen, nuclear engineer at Fairewinds Associates, points out that boric acid leakage inside containment has led to containment liner degradation at a number of U.S. reactors, including Turkey Point, increasing the risk that containments will fail to prevent radioactivity releases during reactor accidents. The U.S. Nuclear Regulatory Commission (NRC) just announced the deployment of a special inspection team to Palisades to investigate this latest leak.

Today, HuffPost Hill has broken the story that NRC's Office of Inspector General (OIG) has launched an investigation into the behavior of NRC Commissioner William C. Ostendorff, for allegedly yelling at a female NRC staffer regarding an investigation ordered by former NRC Chairman Greg Jaczko. Ironically enough, Ostendorff joined three other NRC Commissioners in late 2011, writing the White House that Jaczko's alleged bullying of female NRC staffers had chilled the agency work environment. Pro-nuclear Hill Republicans jumped on the opportunity, carrying out "witch hunt" hearings, which eventually forced the (as investigative journalist and Beyond Nuclear board member Karl Grossman has put it) "insufficiently pro-nuclear" Jaczko's ouster from the agency.

Jaczko had met with an environmental coalition in South Haven, Michigan a short time after having toured the problem-plagued Palisades atomic reactor on May 25th. Jaczko's office had reached out to Beyond Nuclear a month earlier, asking for assistance in setting up the meeting, which included key environmental group representatives from across Michigan, as well as local anti-nuclear watchdogs and concerned residents. However, during the meeting, not a peep was shared with the concerned public about the Safety Injection Refueling Water (SIRW) storage tank leak, into buckets in the control room. Courageous Palisades whistleblowers, their attorney Billie Pirner Garde, and U.S. Representative Ed Markey (D-MA) brought this to light in mid-June.

The coalition immediately wrote Jaczko, asking why he had not informed them about the SIRW storage tank leak at the May 25th meeting. Jaczko never wrote back before leaving office. However, as reported by the HuffPost Hill, he did order an investigation into why his own staff had not informed him of the SIRW storage tank leak --he was as in the dark as the public! Jaczko had been accompanied on his Palisades tour, and at his press conference and meeting with the public afterwards, by NRC Region 3 Administrator Chuck Casto, NRC Office of Public Affairs director Elliot Brenner, several NRC HQ and Region 3 staff persons, as well as NRC's Palisades resident inspectors. It is inconceivable that none of them knew about the SIRW storage tank leak, as it had been ongoing for over a year.

Saturday
Aug112012

NRC FOIA documents regarding Davis-Besse shield building cracking

On January 26, 2012, Beyond Nuclear filed a Freedom of Information Act (FOIA) request to the U.S. Nuclear Regulatory Commission (NRC) after NRC Region 3 Acting Administrator, Cynthia Pedersen, refused to provide documents about her decision to approve the rushed re-start at Davis-Besse, despite "unique" cracking of its concrete containment shield building.

In mid-June, 2012, NRC at long last began to respond to the FOIA request (the response is still not complete). Following are links to NRC's FOIA response, APPENDIX B: (PREVIOUSLY UN-RELEASED) RECORDS BEING RELEASED IN THEIR ENTIRETY documents, cited in Beyond Nuclear and environmental coalition allies' 5th supplement to its cracked concrete containment contention, in opposition to Davis-Besse's 20 year license extension, before NRC's Atomic Safety (sic) and Licensing Board (ASLB):

Appendix B Table of ContentsB/1; B/2; B/3; B/4; B/9; B/10; B/13; B/15; B/16; B/18; B/19; B/21; B/22; B/23; B/24B/25; B/26; B/27; B/28; B/29; B/30; B/31; B/32; B/33; B/34; B/35; B/36; B/37; B/38; B/39; B/40; B/41; B/42; B/43; B/44; B/45; B/46; B/48; B/49; B/50; B/51; B/52; B/53.

A number of these Appendix B documents were cited in Beyond Nuclear's report, "What Humpty Dumpty doesn't want you to know: Davis-Besse's Cracked Containment Snow Job."