NRC Commissioners deny appeal on QA at Fermi 3, but environmental intervenors vow to fight on
December 16, 2014
admin

An artist's rendition of the GEH ESBWR, proposed by DTE to be built as "Fermi 3" at its nuclear power plant in Monroe Co., MIOn Dec. 16th, the U.S. Nuclear Regulatory Commission's (NRC) five Commissioners, in a unanimous ruling, denied an environmental coalition's appeal in the NRC Atomic Safety and Licensing Board (ASLB) proceeding on Detroit Edison's (DTE) proposed new Fermi 3 reactor in southeast MI on the Lake Erie shore. DTE proposes to construct and operate an untested General Electric-Hitachi (GEH), so-called "Economic, Simplified Boiling Water Reactor" (ESBWR) on the very spot where Fermi 1 had a partial meltdown in 1966, immediately adjacent to the Fukushima Daiichi twin-design Fermi 2, a GE Mark I BWR.

The coalition requested reconsideration of the ASLB's June 2014 ruling that DTE's Fermi 3 quality assurance (QA) program was adequate, reasserting its preponderence of evidence -- including the testimony of Fairewinds Associates, Inc.'s Chief Engineer, Arnie Gundersen -- that DTE's QA program was in fact in disarray, or even non-existent. The coalition intends to appeal this NRC ruling, and other pending matters, to the federal courts, if need be. More.

Article originally appeared on Beyond Nuclear (https://archive.beyondnuclear.org/).
See website for complete article licensing information.