FENOC weather seals severely cracked Davis-Besse shield building exterior -- 40 years too late
August 25, 2012
admin

Painters work high off the ground to apply a protective weatherproof coating to Davis-Besse’s concrete Shield Building. Cracks were discovered in the fall that were blamed on the Blizzard of 1978. THE BLADE/AMY E. VOIGTAs reported by the Toledo Blade in an article entitled "Work crews apply waterproof coating to Davis-Besse: Project not silencing critics of plant," the only "corrective action" FirstEnergy Nuclear Operating Company (FENOC) plans to take, in response to severe cracking of its radiological containment "shield building," is to weather seal the exterior of the steel-reinforced concrete structure -- four decades too late. FENOC blames the cracking on the "brutal Blizzard of 1978,"which Beyond Nuclear has dubbed a snow job -- a charge repeated on the floor of the U.S. House of Representatives by long-time Davis-Besse watchdog, Congressman Dennis Kucinich (D-OH), whose constituents live immediately downwind and downstream from the problem-plagued plant. 

The article quoted both Terry Lodge, Toledo-based attorney representing the bi-national environmental coalition (Beyond Nuclear, Citizens Environment Alliance of Southwestern Ontario, Don't Waste Michigan, and the Green Party of Ohio)battling against Davis-Besse's 20-year license extension, as well as Beyond Nuclear's Kevin Kamps:

"I'm not at all comforted that they discovered an error that never should have happened to the most expensive and safety-significant building on the site," Mr. Lodge said Thursday.

Added Kevin Kamps of Beyond Nuclear, "It's 40 years too late. Weather sealant will not fix the cracks that are there."

As reported by Fox 8 Cleveland, a FENOC spokesman outright lied: “The shield building meets all its design parameters, we have evaluated it for all its parameters, and it is fully operable,” said Jon Hook, the design engineer manager at the plant.

In fact, both the U.S. Nuclear Regulatory Commission and FENOC itself have acknowledged that Davis-Besse's severe shield building cracking violates the atomic reactor's design and licensing bases. At an August 9th public meeting in Oak Harbor, OH, an NRC spokesman, with an audible scoff, admitted that NRC has generously granted FENOC until December 2012 to merely come up with a "plan for a plan" to "restore conformance" -- that is, pencil whip the violations, making everything appear okay on paper.  

Hook also told the Toledo Blade the shield building "wasn't coated originally because 'there was no requirement that it be done...'." Why such a basic no brainer as weather sealant was not required -- on the shoreline of Lake Erie, which suffers severe winter weather -- has never been explained, neither by FENOC nor NRC. Further deepening the mystery is the fact that all other -- much less safety significant and expensive -- concrete structures on site were weather sealed. When asked to explain, FENOC spokeswoman Jennifer Young has simply said it was done for aesthetic reasons, as those other structures appeared "splotchy." 

WNWO also reported on this story.

Article originally appeared on Beyond Nuclear (https://archive.beyondnuclear.org/).
See website for complete article licensing information.